Skip to content
XALANTEdge

Edge · Xalant Edge · Solutions → Edge in a Box

Edge · Solution

Edge in a Box

A containerized micro data center: white space, cooling, power and uplink as pre-integrated modules.

What it is

A containerized micro data center — white space, cooling, power and uplink as pre-integrated modules.

A containerized micro data center: white space, cooling, power and uplink as pre-integrated modules. It is the smallest unit on the Xalant ladder and the one every larger unit is built out of.

The bottleneck this answers is not chips. It is the three things a chip needs and cannot get quickly: a site, power on that site, and a path off it. A conventional build treats those as three programmes with three timelines, and the longest of them sets the date. Integrating them into one enclosure is what moves the date.

Every element ships as a factory-integrated container — site work is pads, conduit and connections, not construction.

Specification

What is settled, and what is not

The list below is what the unit is. The figures that go with it are held back until each one has a named basis and an as-of date — Xalant is pre-formation with no live sites, so a number here would be a design target dressed as a measurement. Each row appears on this page the day its figure clears.

What the specification will describe

Enclosure
Factory-integrated, on a container footprint
Cooling
N+1 precision air, pre-piped for liquid
Power
Ride-through, dual-feed distribution
Fire
Early detection, clean-agent suppression
Security
Access control and camera coverage
Path off site
Meet-me room, satellite first, fibre later
Site work
Pads, conduit and connections
Utility
Nothing on the pad is designed to depend on one
  • IT design loadThe load the whole container is sized around, from the rack line to the switchgear.
  • White spaceThe footprint a site host has to find room for on a pad.
  • RacksHow much of a rack line fits in one container before a second one is needed.
  • Per-rack design loadWhat can go in a rack before the cooling line has to change.
  • Design PUEHow much electrical load the site needs for every unit of IT load.
  • Free-cooling thresholdThe outside temperature below which the plant is designed to cool on ambient air alone.
  • UPS ride-throughHow long the hall is designed to hold up while power transfers.

Design rule

Every element ships as a factory-integrated container — site work is pads, conduit and connections, not construction.

That is the whole design. A conventional build treats site, power and the path off it as three programmes, and the longest one sets the date. Integrating them into one enclosure is what moves the date.

Design intent, not an operating record

Against a conventional build

The difference is what is on the critical path

No duration is compared here. That comparison needs a public source for the interconnection queue and for the fibre lead time in each market, and there is not one in this repository yet — so what is compared is how the two are built.

Two approaches to the same site, compared by method rather than by duration
AspectA conventional buildEdge in a Box
What sets the dateThe grid interconnection queue, and it is set by the utility rather than by the project.The local approval path. Everything else is designed to be inside the fence line.
What happens on the padConstruction — shell, fit-out, plant, commissioning, in sequence.Pads, conduit and connections. The enclosure arrives integrated.
Where the risk sitsOn site, where a delay in one trade delays the trades after it.In the factory, where the same build is repeated and the site work is short.
Growing it laterA second project, with its own design and its own approvals.Another module on the same spine, from the same drawings.
If the load changesThe building is already the size it is.The unit is the container, so the step size is one container.
PowerA utility connection, with a queue position and a tariff.On-site generation. Nothing on the pad is designed to depend on a public utility.

The pod

What ships in every container

IT WHITE SPACECOOLINGUPSSWITCHGEARMEET-ME & UPLINK
Edge in a Box, plan view, uplink end to the right
  1. IT white space

    The rack line with hot and cold aisle containment. Everything else in the enclosure is sized from it.

  2. N+1 precision air

    Redundant cooling, designed for free cooling on ambient air below the design threshold and pre-piped for direct-to-chip liquid.

  3. UPS and battery room

    Ride-through and dual-feed distribution, with early smoke detection and clean-agent suppression in the same room.

  4. Switchgear and genset tie-in

    Where on-site generation lands. Gensets, storage and solar are designed onto one bus.

  5. Meet-me room and uplink

    Where the satellite path meets the terrestrial network, and where fibre lands in a later phase.

Deployment

Five steps to a running pad

Steps two and three are where the time goes, and only one of them is ours.

  1. Assess the pad

    Ground, access, setbacks and where the power lands. A day on site, not a survey programme.

  2. Permit

    The local approval path. Its duration belongs to the jurisdiction and sits outside every figure Xalant quotes.

  3. Prepare

    Pads, conduit and connections. This is the only construction on the critical path.

  4. Land the module

    The enclosure arrives integrated. What happens on the pad is connection, not assembly.

  5. Commission

    Cooling and the rack line are commissioned together, then acceptance is run against the published design specification.

Questions

Asked and answered

Is this a shipping container with racks in it?
It is a purpose-built enclosure on a container footprint. White space, cooling, power distribution, ride-through and the meet-me room are all integrated in the factory, so what happens on the pad is pads, conduit and connections rather than construction.
What does the site have to provide?
A prepared pad, a route for conduit, and a power connection from the on-site generation. Nothing on the pad is designed to depend on a public utility.
Can it take liquid-cooled racks?
The cooling is specified as N+1 precision air with the pipework and floor loading for direct-to-chip liquid. A rack line that needs liquid from the start is the Edge Campus tier rather than this one.
Do the published figures mean a site is running today?
No. Xalant is pre-formation and has no live sites. Every figure on this page is a design target, and none of them is published here until its basis and its as-of date are cleared.
Is there a datasheet?
The one-pager is ungated and published as soon as the spec figures clear. Until then, ask and we will send what is settled and say plainly what is not.
Line drawing of the Xalant campus: the hall row, the substation and the gateway dish, derived from a reference render.

Reference render

The campus, drawnAI render — reference only

Site & capacity · Request

Tell us what the pad looks like and we will tell you what lands on it.